Suspension of Inotera’s Fab Disrupts DRAM Market; TrendForce Forecasts 5.5% Reduction in Global Production Capacity in July and Further Price Increases

Inotera, which is also known as Micron Technology Taiwan, suspended the operation of Fab-2, one of its two fabrication plants in Taiwan’s Taoyuan City, on July 1. The malfunctioning of the nitrogen gas dispensing system led to the contamination of wafers and equipment in the facility. DRAMeXchange, a division of TrendForce, estimates that Inotera has suffered a production capacity loss of around 60K wafer starts per month, out of the supplier’s previous total of 125K wafer starts per month (K = 1,000). This conservative estimate also amounts to a 5.5% cut in the global DRAM production capacity for this July. The temporary shutdown of Fab-2 is expected to aggravate the current undersupply situation in the DRAM market and cause further price increases for memory products.

DRAMeXchange points out that 60K capacity loss figure excludes the number of wafers not being processed by Fab-2 during this period of shutdown from July 1 up to now. Inotera plans to have Fab-2 resume operation as soon as possible, but the cleaning and the restoration of production capacity will be a time-consuming challenge.

DRAMeXchange puts the average monthly production capacity of the entire DRAM industry at 1,135K wafer starts for this third quarter, while Fab-2 is estimated to have achieved a monthly capacity of 60K prior to the contamination event. With Fab-2 suspending operation, the global DRAM production capacity for July has been reduced by 5.5%.

Inotera’s product mix includes PC, server and mobile DRAM products. Hence, a production disruption from its end coupled with the already strained supply situation will have an impact on all segments of the DRAM market.

Inotera is also mainly responsible for manufacturing Micron’s LPDDR4 products that go into Apple’s supply chain for iPhone. The temporary shutdown of Fab-2 could have an impact on shipments of the upcoming new iPhone devices as well.

Both DRAM buyers and suppliers are still weighing the extent of damages caused by the contamination event at Fab-2. The negotiation pertaining to the third-quarter contracts are likely to be affected by some uncertainty over whether the facility can quickly resume operation. Some suppliers are already hinting that price hikes are on the horizon. While the event’s long-term effect on DRAM market remains to be seen, DRAMeXchange expects tighter squeeze on the supply and strengthening of the current price upswing.

Read more at https://press.trendforce.com/press/20170705-2897.html#dodzibkrDMbg1gAD.99

Liat

Recent Posts

IEEE Study Develops a Compact Metalens That Keeps Images Sharp Across Different Distances

Researchers develop a metasurface that combines an optical lens and focus-correcting functionalities into one flat…

4 days ago

Teradar Announces New German Headquarters to Accelerate Testing and Commercialization of its Pioneering Terahertz Vision and Sensing Products for Autonomous Vehicle Advancement in Europe

Teradar GmbH will strengthen European competitiveness in global self-driving vehicle markets with "Made in Europe"…

4 days ago

CANoe Automates Development and Testing Workflows with AI Agents

With new AI agents and the Model Context Protocol (MCP), CANoe executes complete workflows via…

4 days ago

IBM Connects Its First Modular Cryogenic Systems in Milestone Toward Fault-Tolerant Quantum Computing

• New cryogenic quantum fridges designed to link hundreds of quantum chips. • Cooled to…

4 days ago

Analog Devices Posts Record Q3 Revenue as Industrial and Data Center Demand Accelerates

Analog Devices (ADI) reported record revenue of $4.02 billion for its fiscal third quarter of…

4 days ago

New-Tech Europe | Q3 2026 | Digital Edition

New-Tech Europe | Q3 2026 | Digital Edition

2 weeks ago